Contracting Strategies for Electrolyzers to Secure Grid Connection: The Dutch Case

Thomas Swarts, Jalal Kazempour, Wouter van den Akker, Johan Morren, Arjan van Voorden, Han Slootweg

发表年份
2025
访问权限
开放获取

摘要

In response to increasing grid congestion in the Netherlands, non-firm connection and transport agreements (CTAs) and capacity restriction contracts (CRCs) have been introduced, allowing consumer curtailment in exchange for grid tariff discounts or per-MW compensations. This study examines the interaction between an electrolyzer project, facing sizing and contracting decisions, and a network operator, responsible for contract activations and determining grid connection capacity, under the new Dutch regulations. The interaction is modeled using two bilevel optimization problems with alternating leader-follower roles. Results highlight a trade-off between CRC income and non-firm CTA tariff discounts, showing that voluntary congestion management by the network operator increases electrolyzer profitability at CRC prices below 10 euro per MW but reduces it at higher prices. Furthermore, the network operator benefits more from reacting to the electrolyzer owner's CTA decisions than from leading the interaction at CRC prices above 10 euro per MW. Ignoring the other party's optimization problem overestimates profits for both the network operator and the electrolyzer owner, emphasizing the importance of coordinated decision-making.

关键词

math.OCeess.SY

相关论文

查看 OTHER 分类全部论文